Conditions / Refusal Reasons
The development to which this permission relates must be begun not later than the expiration of three years beginning with the date of this permission.
Reason: By virtue of Sections 91 to 95 of the Town and Country Planning Act 1990 as amended by section 51 of the Planning and Compulsory Purchase Act 2004.
That the development hereby approved shall be carried out in accordance with the details shown on the approved plans list set in the additional information letter dated 08/05/2025 from Edgars Planning referenced 1064/3670, except as controlled or modified by conditions of this permission.
Reason: To secure the proper planning of the area in accordance with Development Plan policies.
A Construction Traffic Management Plan (CTMP) shall be submitted to and approved in writing by the Local Planning Authority prior to the commencement of development. The approved CTMP shall be implemented prior to any works being carried out on site, and shall be maintained throughout the course of the development.
Reason: In the interests of highway safety and to mitigate the impact of construction vehicles on the surrounding highway network, road infrastructure and local residents, particularly at morning and afternoon peak traffic times and in accordance with Policy TRANS5 of the South Oxfordshire Local Plan 2035.
Prior to the construction of any development above slab level a scheme for the landscaping of the site, including boundary treatments and the planting of live trees and shrubs, shall be submitted to and approved in writing by the Local Planning Authority. These details shall include schedules of new trees and shrubs to be planted (noting species, plant sizes and numbers/densities), the identification of the existing trees and shrubs on the site to be retained (noting species, location and spread), any earth moving operations and finished levels/contours, and an implementation programme. The scheme shall be implemented prior to the first occupation or use of the development hereby approved or in relation to planting no later than the first planting season following first occupation, and thereafter be maintained in accordance with the approved scheme. In the event of any of the trees or shrubs so planted dying or being seriously damaged or destroyed within 5 years of the completion of the development, a new tree or shrub or equivalent number of trees or shrubs, as the case may be, of a species first approved by the Local Planning Authority, shall be planted and properly maintained in a position or positions first approved in writing by the Local Planning Authority.
Reason: To help to assimilate the development into its surroundings in accordance with Policies ENV1, DES1 and DES2 of the South Oxfordshire Local Plan 2035.
Prior to the commencement of the development above slab level, details (including specification, position, height, orientation) of a scheme of features to be provided for protected and priority species, shall be submitted to and approved in writing by the local planning authority. The scheme shall be designed in conjunction with a suitably qualified ecologist and bird/bat boxes on buildings shall be integrated into the fabric of the development. A minimum number of biodiversity enhancement features shall be provided onsite as follows: two integrated bird nest boxes for house sparrow Passer domesticus or swift Apus apus and two integrated bat boxes. Thereafter, the development shall be implemented in accordance with the approved details. All features shall be provided prior to first use and shall be retained and maintained thereafter.
REASON: To secure biodiversity enhancements onsite, in accordance with Policy ENV2 of the South Oxfordshire Local Plan, The South and Vale Joint Design Guide and paragraphs 187d and 193d of the NPPF
No development above slab level shall take place until a photographic schedule of all materials to be used in the external construction and finishes of the development hereby permitted has been submitted to and approved in writing by the Local Planning Authority.
Reason: In the interests of the visual appearance of the development in accordance with Policies DES1 and DES2 of the South Oxfordshire Local Plan 2035.
Cycle parking facilities shall be provided prior to the occupation of the development hereby approved in accordance with the details shown on drawing no.759-MICA-XX-00-DR-A19200, Rev PL1. Thereafter, the cycle parking shall be retained as approved.
Reason: To encourage the use of cycles as a means of transport in accordance with Policy TRANS5 of the South Oxfordshire Local Plan 2035.
Prior to first occupation, all carbon reduction energy efficiency measures shall be implemented in accordance with the Energy Statement hereby approved and a Verification Report shall be submitted to the Local Planning Authority and approved in writing. The Verification Report shall demonstrate (with photographic evidence) that the energy efficiency measures have been implemented. These measures shall be retained and maintained as such thereafter in accordance with the Energy Statement and Verification Report.
Reason: To ensure high standards of sustainable design and construction in accordance with Policy DES10 of the South Oxfordshire Local Plan 2035.
The privacy screen shown on the approved plans for the first floor apartment within 120 Broadway shall be implemented as approved prior to first occupation of the development hereby approved and shall thereafter be retained in situ.
Reason: To ensure that the development is not unneighbourly in accordance with Policy DES6 of the South Oxfordshire Local Plan 2035
Prior to first occupation, the existing vehicular access to the Broadway shall be closed and shall not be used by any vehicular traffic whatsoever. Pedestrian and cycle access shall be in accordance with 759-MICA-XX-XX-DR-A-19020-PL1.
Reason: In the interest of highway safety in accordance with Policy TRANS5 of the South Oxfordshire Local Plan 2035.
Prior to the occupation of any dwelling, a drainage plan and construction details containing a suitable inspection turret for example SDS GEOlight must be submitted and approved by the Local Planning Authority. The approved plans shall be implemented in accordance with the approved details prior to the occupation of the development hereby approved.
Reason: To prevent pollution and flooding in accordance with Policies ENV12 and EP4 of the South Oxfordshire Local Plan 2035.
Prior to the occupation of any dwelling, a SUDS Compliance report prepared by an appropriately qualified Engineer must be submitted to and approved by the Local Planning Authority. This must suitably demonstrate that the sustainable drainage system has been installed and completed in accordance with the approved scheme (or detail any minor variations). This report should as a minimum cover the following;
1) Inclusion of as-built drawings in DWG or DXF format,
2) Inspection details of key SUDS features such as flow controls, storage features and
volumes and critical linking features or pipework undertaken, with appropriate photographs
and evidence of inspections incorporated,
3) Details of any remediation works required following the initial inspection,
4) Evidence that that remedial works have been completed.
5) CCTV survey.
Reason: To ensure the proper provision of surface water drainage and to ensure flooding is not exacerbated in the locality in accordance with Policy EP4 of the South Oxfordshire Local Plan 2035.
Prior to the occupation of any dwelling, a compliance report prepared by an appropriately qualified Engineer must be submitted to and approved by the Local Planning Authority. This must suitably demonstrate that the foul drainage system has been installed and completed in accordance with the approved scheme (or detail any minor variations). This report should as a minimum cover the following;
1) Inclusion of as-built drawings in DWG or DXF format,
2) Inspection details of key features such as manholes, pipe runs undertaken, with appropriate photographs and evidence of inspections incorporated,
3) Details of any remediation works required following the initial inspection,
4) Evidence that that remedial works have been completed.
5) CCTV survey.
Reason: To ensure the proper provision of foul water drainage and to ensure flooding and pollution is not exacerbated in the locality in accordance with policy EP4 of the South Oxfordshire Local Plan 2035.
That, unless otherwise agreed in writing by the local planning authority the development shall be carried out in accordance with the detail set out in the Noise Assessment Technical Report R10113-1 Rev1 dated 22 July 2024 prior to the occupation of the development.
Reason: To safeguard the amenities of the occupiers of the proposed development in accordance with Policy ENV11 of the South Oxfordshire Local Plan 2035.