Conditions / Refusal Reasons
The development to which this permission relates must be begun not later than the expiration of three years beginning with the date of this permission.
Reason: By virtue of Sections 91 to 95 of the Town and Country Planning Act 1990 as amended by section 51 of the Planning and Compulsory Purchase Act 2004.
That the development hereby approved shall be carried out in accordance with the details shown on the following approved plans, 23A050_PL03 B, 23A050_PL01, 23A050_PL04 A, 23A050_PL10D, 23A050_PL02 A, 23A050_PL06 A, 23A050_PL20 A, 23A050_PL09 A, 23A050_PL23 A, 23A050_PL07 A, 23A050_PL08 A, BNGD PLAN 23A050PL15, 23A050_PL21 A, 23A050_PL22 B, 23A050_PL05, 23A050_PL11D, 23A050_PL30, 23A050_PL31, 23A050_PL32, 23A050_PL33 and 23A050_PL34, except as controlled or modified by conditions of this permission.
Reason: To secure the proper planning of the area in accordance with Development Plan policies.
The exterior of the development hereby permitted shall only be constructed in the materials specified on the plans/supporting documents hereby approved or in materials which shall previously have been approved in writing by the Local Planning Authority.
Reason: In the interests of the visual appearance of the development in accordance with Policies DES1 and DES2 of the South Oxfordshire Local Plan 2035.
No development shall commence until a Habitat Management and Monitoring Plan (HMMP) has been submitted to, and approved in writing by, the Local Planning Authority. The HMMP shall be consistent with, and submitted alongside, the associated Biodiversity Gain Plan and include:
1) a non-technical summary;
2) the roles and responsibilities of the people or organisation(s) delivering the HMMP;
3) the planned habitat creation and enhancement works to create or improve habitat to achieve the Biodiversity Net Gain in accordance with the associated Biodiversity Gain Plan;
4) the management measures to maintain habitat in accordance with the approved Biodiversity Gain Plan for a period of 30 years from the substantial completion* of development; and
5) the monitoring methodology (including the specification of subsequent required monitoring reports) to be provided to the Local Planning Authority at monitoring intervals. The monitoring intervals shall be at years 1, 2, 5, 10, 15, 20, 25 and 30, after the substantial completion* of development.
Thereafter, the created and/or enhanced habitat approved by the associated Biodiversity Gain Plan shall be implemented in accordance with the approved HMMP.
All subsequent monitoring reports shall be submitted to, and approved in writing by, the Local Planning Authority, in accordance with the methodology and frequency specified in the approved HMMP.
(*substantial completion is taken to be when the landowner can occupy the development to use it for its approved purpose AND all establishing habitat creation and enhancement works, as set out in the approved HMMP, have been implemented successfully).
Reason: To ensure the development delivers a Biodiversity Net Gain onsite (Policy ENV3 of the South Oxfordshire Local Plan, and in accordance with Schedule 7A of the Town and Country Planning Act 1990).
Following the approval of the Habitat Management and Monitoring Plan (HMMP) referred to in condition 4, no use and/or occupation of the development shall take place until clear and unambiguous evidence confirming that the development is substantially complete*, has been submitted to, and approved in writing by, the Local Planning Authority. The date of substantial completion shall be confirmed in that evidence.
(*substantial completion is taken to be when the landowner can occupy the development to use it for its approved purpose AND all establishing habitat creation and enhancement works, as set out in the approved HMMP, have been implemented successfully).
Reason: To ensure the development delivers a Biodiversity Net Gain on site (Policies CP45/46/ENV3, and in accordance with Schedule 7A of the Town and Country Planning Act 1990).