Description
Extension of Sewage Treatment Works to provide new inlet works elevation screen, balancing tank, above ground pipework, washwater booster station, motor control centre, standby generator and bulk fuel storage, break in chamber, security fence, flow control tank and pumping station, security fencing and associated works.
Consultation / Notification
No further Representations on this application will be accepted.
Consultations / Notifications to date are shown below.
If the response has been scanned, you can access the document by clicking the folder icon alongside the relevant consultee. Folders with a
*
alongside them indicate new content within the folders (i.e. new documents added within the last 7 days)
Name / Number
Date Sent
Response Date
Scanned Response