Conditions / Refusal Reasons
The development to which this permission relates must be begun not later than the expiration of three years beginning with the date of this permission.
Reason: By virtue of Sections 91 to 95 of the Town and Country Planning Act 1990 as amended by section 51 of the Planning and Compulsory Purchase Act 2004.
That the development hereby approved shall be carried out in accordance with the details shown on the following approved plans, 012_C, 014_C, 150_F, 160_E, 161_E, 162_E, 090_C, 060_A, 051_C, 002_C, 004_A, 163_E and 164_E, except as controlled or modified by conditions of this permission.
Reason: To secure the proper planning of the area in accordance with Development Plan policies.
The exterior of the development hereby permitted shall only be constructed in the materials specified on the plans/supporting documents hereby approved or in materials which shall previously have been approved in writing by the Local Planning Authority.
Reason: In the interests of the visual appearance of the development in accordance with Policies DES1 and DES2 of the South Oxfordshire Local Plan 2035.
The tree protection details as shown in the approved Tree Survey Report, Impact Appraisal and Tree Protection Details dated October 2024 shall be put in place prior to any on site works including demolition and thereafter retained in situ for the duration of development.
Reason: To safeguard trees which are visually important in accordance with Policies ENV1, DES1, and DES2 of the South Oxfordshire Local Plan 2035.
Prior to the construction of any development above slab level a scheme for the landscaping of the site, including the planting of live trees and shrubs, shall be submitted to and approved in writing by the Local Planning Authority. These details shall include schedules of new trees and shrubs to be planted (noting species, plant sizes and numbers/densities), the identification of the existing trees and shrubs on the site to be retained (noting species, location and spread), any earth moving operations and finished levels/contours, and an implementation programme. The scheme shall be implemented prior to the first occupation or use of the development hereby approved and thereafter be maintained in accordance with the approved scheme. In the event of any of the trees or shrubs so planted dying or being seriously damaged or destroyed within 5 years of the completion of the development, a new tree or shrub or equivalent number of trees or shrubs, as the case may be, of a species first approved by the Local Planning Authority, shall be planted and properly maintained in a position or positions first approved in writing by the Local Planning Authority.
Reason: To help to assimilate the development into its surroundings in accordance with Policies ENV1, DES1 and DES2 of the South Oxfordshire Local Plan 2035.
No development shall take place, including vegetation clearance, demolition or ground works, unless and until a Construction Method Statement for protected species is submitted to and approved in writing by the Local Planning Authority. This shall be produced by a suitably qualified ecologist, based on Sections 6.2.2, 6.2.9, 6.2.12 and Appendix 6 of the Preliminary Ecological Appraisal Report submitted with the planning application (Smart Ecology dated 13 October 2023). The statement shall describe Reasonable Avoidance Measures to be employed during construction to avoid impacts on:
1. Badger, hedgehog and other small animals (including measures to be employed to avoid these species becoming trapped in excavations)
2. Nesting birds (including vegetation clearance timings and/or arrangements for ecological supervision)
3. Reptiles and amphibians (including details of a directional two-stage cutting regime to encourage any reptiles out of the works area, rules for siting building materials and waste to avoid them being used as temporary refuges).
The Construction Method Statement shall include the procedure to be followed in each case if a protected species is found on site. The approved Construction Method Statement shall be adhered to and implemented throughout the construction period strictly in accordance with the approved details.
Reason: To avoid impacts on protected species during construction, in line with Policy ENV2 of the South Oxfordshire Local Plan.
No external lighting shall be installed on site unless and until a sensitive lighting strategy for bats is submitted to and approved in writing by the Local Planning Authority. The strategy shall protect the conservation status of local bat populations, by:
a) identifying those areas/features on site that are likely to be both sensitive for bats and vulnerable to disturbance from artificial lighting, including: known or potential breeding sites, resting places, foraging areas or important routes used to access key areas of their territory.
b) demonstrating that the design and siting of the proposed lighting installation will not disturb or prevent bats using the areas identified in a) (through provision of appropriate lighting plans, isolux contour maps and technical specifications)
All external lighting shall be installed in accordance with the specifications and locations set out in the approved strategy. Under no circumstances should any other external lighting be installed without the written approval of the local planning authority.
Reason: To protect the appearance of the area, the environment and wildlife, and local residents from light pollution in accordance with Policies ENV1, ENV2, ENV3 and ENV12 of the South Oxfordshire Local Plan 2035.
The first-floor windows in the northwest (side) elevation of the extension hereby permitted shall be both glazed in obscure glass with a minimum of level 3 obscurity and fixed shut, where below 1.7m from finish floor level in each associated room. The measures shall be applied prior to the first occupation of the accommodation and shall be retained as such thereafter.
Reason: To ensure that the development is not unneighbourly in accordance with Policy DES6 of the South Oxfordshire Local Plan 2035.