Conditions / Refusal Reasons
The development to which this permission relates must be begun not later than the expiration of three years beginning with the date of this permission.
Reason: By virtue of Sections 91 to 95 of the Town and Country Planning Act 1990 as amended by section 51 of the Planning and Compulsory Purchase Act 2004.
That the development hereby approved shall be carried out in accordance with the details shown on the following approved plans, 5917-C258-ICS-01-XX-DR-C-0200-S2-P02, C258-01, C258-02, C258-10, C258-04-B, C258-05-B, C258-06-A, C258-07-A, C258-08-B and C258-09-B, except as controlled or modified by conditions of this permission.
Reason: To secure the proper planning of the area in accordance with Development Plan policies.
Prior to the commencement of development, with the exception of any demolition, a full surface water drainage scheme shall be submitted to, and approved in writing by, the Local Planning Authority. The design of the surface water drainage system shall be in accordance with the non-statutory technical standards for sustainable drainage systems, including details of BRE 365 soakage testing, levels, size, position and construction of all drainage works. The drainage scheme shall be sized to accommodate a minimum of the worst case 1 in 30 year storm, with evidence to demonstrate that the site can accommodate the worst case 1:100 year storm + 40% Climate Change storm, without any flows exiting up to this storm event and any storage on site not causing a nuisance or flooding to property. The approved scheme shall be implemented in accordance with the approved details prior to the occupation of the development hereby approved.
Notes
Cv values must be set at 0.95.
An exceedance plan must be provided.
Each building must contain a bio retention/source control feature. This could be in the form of a rain water planter or rain water butt.
Full construction details of all surface water drainage components including hard standing areas, must be provided.
Drainage layout from RWP must be provided.
A manhole schedule must be provided.
A maintenance strategy, inclusive ownership for the entirety of the surface water drainage system must be provided. This must be supported by a coloured coded plan, where shared features are proposed.
The applicant must consider Ciria C574. The area is shown to be at medium risk of subsidence.
Reason: To prevent pollution and flooding in accordance with Policies ENV12 and EP4 of the South Oxfordshire Local Plan 2035.
Prior to the commencement of development, with the exception of any demolition, a full foul water drainage scheme shall be submitted to and approved in writing by the Local Planning Authority. The drainage scheme shall include details of BS6297 percolation testing, method, levels, size, position and construction of the drainage scheme.
Notes
Hydraulic calculations must be provided.
Full construction details of all foul water drainage components must be provided.
Drainage layout from SVP must be provided.
A manhole schedule must be provided.
Reason: To ensure the proper provision of foul water drainage and to ensure flooding and pollution is not exacerbated in the locality in accordance with policy EP4 of the South Oxfordshire Local Plan 2035.
Prior to any works starting on site, a Construction Method Statement for protected species shall be submitted to and approved in writing by the Local Planning Authority. This shall be produced by a suitably qualified ecologist and shall describe Reasonable Avoidance Measures to be employed during construction to avoid impacts on:
1. Badger, hedgehog and other small animals (including measures to be employed to avoid these species becoming trapped in excavations)
2. Nesting birds (including vegetation clearance timings and/or arrangements for ecological supervision)
The approved Construction Method Statement shall be adhered to and implemented throughout the construction period strictly in accordance with the approved details.
REASON: To avoid impacts on protected species during construction, in line with Policy ENV2 of the South Oxfordshire Local Plan.
Prior to the construction of any development above slab level a scheme for the landscaping of the site, including the planting of live trees and shrubs, shall be submitted to and approved in writing by the Local Planning Authority. These details shall include schedules of new trees and shrubs to be planted (noting species, plant sizes and numbers/densities), the identification of the existing trees and shrubs on the site to be retained (noting species, location and spread), any earth moving operations and finished levels/contours, and an implementation programme. The scheme shall be implemented prior to the first occupation or use of the development hereby approved and thereafter be maintained in accordance with the approved scheme. In the event of any of the trees or shrubs so planted dying or being seriously damaged or destroyed within 5 years of the completion of the development, a new tree or shrub or equivalent number of trees or shrubs, as the case may be, of a species first approved by the Local Planning Authority, shall be planted and properly maintained in a position or positions first approved in writing by the Local Planning Authority.
Reason: To help to assimilate the development into its surroundings in accordance with Policies ENV1, DES1 and DES2 of the South Oxfordshire Local Plan 2035.
No development above slab level shall take place until a photographic schedule of all materials to be used in the external construction and finishes of the development hereby permitted has been submitted to and approved in writing by the Local Planning Authority.
Reason: In the interests of the visual appearance of the development in accordance with Policies DES1 and DES2 of the South Oxfordshire Local Plan 2035.
Prior to the first occupation of the development hereby approved, a Biodiversity Enhancement Plan (BEP) shall be submitted to and approved in writing by the Local Planning Authority. The BEP should include:
1. Description and evaluation of features to be managed, including extent and location of the proposed works.
2. Ecological trends and constraints on site that might influence management.
3. Aims and objectives of management.
4. Method statements providing details of how habitats will be created or enhanced and subsequently maintained, in line with the aims and objectives. These should cross reference relevant landscape plans, include suitably detailed additional drawings and cross sections as required, and describe sources of habitat materials (e.g. plant stock).
5. Method statements providing details of how enhancement features for protected species shall be installed and subsequently maintained, in line with the aims and objectives. These should include plans and drawings showing the location, elevation, orientation and specification of features. Features on the proposed building shall be integrated into its structure to ensure their longevity. A minimum number of features shall be provided on site as follows: one integrated bird nest box for house sparrow Passer domesticus or swift Apusapus, and two integrated bat boxes.
6. Preparation of a work schedule (including an annual work plan capable of being rolled forward over a 30-year period).
7. Details of the body or organization responsible for implementation of the plan.
8. Ongoing monitoring and remedial measures.
Thereafter, the habitats and enhancement features shall be developed on site and retained in accordance with the approved details. All enhancements shall be delivered prior to the final occupation of the development.
REASON: To ensure that habitats are created and managed for biodiversity to maximise their ecological value and deliver a biodiversity net gain, in accordance with Policies ENV2 and ENV3 of the South Oxfordshire Local Plan
Prior to first occupation, all carbon reduction energy efficiency measures shall be implemented in accordance with the Energy Statement hereby approved and a Verification Report shall be submitted to the Local Planning Authority and approved in writing. The Verification Report shall demonstrate (with photographic evidence) that the energy efficiency measures have been implemented. These measures shall be retained and maintained as such thereafter in accordance with the Energy Statement and Verification Report.
Reason: To ensure high standards of sustainable design and construction in accordance with Policy DES10 of the South Oxfordshire Local Plan 2035.
Prior to the first occupation of the development hereby approved, an Electric Vehicle Charging Point shall be installed for each dwelling and thereafter retained as such.
Reason: To ensure sustainable forms of transport in accordance with Policies TRANS5, ENV12 and EP1 of the South Oxfordshire Local Plan 2035.
No external lighting shall be installed on site unless and until a sensitive lighting strategy for bats is submitted to and approved in writing by the Local Planning Authority. The strategy shall:
a) identify those areas/features on site that are likely to be both particularly sensitive for bats and vulnerable to disturbance from artificial lighting, including: known or potential breeding sites, resting places, foraging areas or important routes used to access key areas of their territory.
b) show how and where external lighting will be installed (through provision of appropriate lighting plans, isolux contour maps and technical specifications) so that it can be clearly demonstrated that areas to be lit will not disturb or prevent bats using their territory or having access to their breeding sites or resting places.
All external lighting shall be installed in accordance with the specifications and locations set out in the strategy. Under no circumstances should any other external lighting be installed without the prior consent from the local planning authority.
REASON: to avoid impacts on bats from insensitive external lighting in line with Policy ENV2 of the South Oxfordshire Local Plan
The developer shall confirm in writing to the Local Planning Authority the presence of any unsuspected contamination encountered during the development. In the event of any contamination to the land and/or water being encountered, no development shall continue until a programme of investigation and/or remedial works to include methods of monitoring and certification of such works undertaken. Where land contamination investigation/remedial works are required this must be carried out by a competent person in accordance with current government and Environment Agency Guidance and Approved Codes of Practice such as Land Contamination: Risk Management 2020 and BS10175:2011 +A2:2017 'Investigation of potentially contaminated sites' and submitted to and approved in writing by the local planning authority.
Reason: To ensure that any ground, water and associated gas contamination is identified and adequately addressed to ensure the safety of the development, the environment and to ensure the site is suitable for the proposed use in accordance with Policy ENV11 of the South Oxfordshire Local Plan 2035.
Notwithstanding the provisions of the Town and Country Planning (General Permitted Development) Order 2015 (or any Order revoking or re-enacting that Order) the provision within the curtilage of the dwelling of any building, enclosure or swimming pool as described in Schedule 2, Part 1, Class E of the Order shall not be undertaken without obtaining planning permission from the Local Planning Authority.
Reason: To safeguard the special landscape of Chilterns National Landscape in accordance with Policies ENV1 of the South Oxfordshire Local Plan 2035.