The development to which this permission relates must be begun not later than the expiration of three years beginning with the date of this permission.
Reason: By virtue of Sections 91 to 95 of the Town and Country Planning Act 1990 as amended by section 51 of the Planning and Compulsory Purchase Act 2004.
That the development hereby approved shall be carried out in accordance with the details shown on the following approved plans, PFHW-SU-099, PFHW-SK-099G and PFHW-SK-098B, except as controlled or modified by conditions of this permission.
Reason: To secure the proper planning of the area in accordance with Development Plan policies.
The exterior of the development hereby permitted shall only be constructed in the materials specified on the plans/supporting documents hereby approved and those approved under P24/S2207/HH or in materials which shall previously have been approved in writing by the Local Planning Authority.
Reason: In the interests of the visual appearance of the development in accordance with Policies DES1 and DES2 of the South Oxfordshire Local Plan 2035.
The tree protection details as shown on the approved plan PFHW-SK-098B shall be put in place prior to any on site works including demolition and thereafter retained in situ for the duration of development.
Reason: To safeguard trees which are visually important in accordance with Policies ENV1, DES1, and DES2 of the South Oxfordshire Local Plan 2035.
Prior to the commencement of the development above new slab level, details (including specification, position, height, orientation) of a scheme of biodiversity enhancements to be provided, shall be submitted to and approved in writing by the local planning authority. The scheme shall be designed in conjunction with a suitably qualified ecologist and bird/bat boxes shall be integrated into the fabric of the development. A minimum of two biodiversity enhancement features shall be provided onsite. Thereafter, the development shall be implemented in accordance with the approved details and all features provided prior to first use.
Reason: To secure biodiversity enhancements onsite, in accordance with Policy ENV3 of the South Oxfordshire Local Plan 2035 and paragraphs 174 and 180 of the NPPF.
Related application(s):
P25/S0094/DISThe applicant, or their agents or successors in title, shall be responsible for organising and implementing an archaeological watching brief, to be maintained during the period of construction/during any groundworks taking place on the site. The watching brief shall be carried out by a professional archaeological organisation in accordance with a Written Scheme of Investigation that has first been submitted to and approved in writing by the Local Planning Authority.
Reason - To safeguard the recording and inspection of matters of archaeological importance on the site in accordance with Policy ENV9 of the South Oxfordshire Local Plan 2035 and the NPPF (2023).
Related application(s):
P25/S0094/DISNo development shall commence on site without the appointed archaeologist being present other than in accordance with the submitted written scheme of investigation. Once the watching brief has been completed its findings shall be reported to the Local Planning Authority, as agreed in the Written Scheme of Investigation, including all processing, research and analysis necessary to produce an accessible and useable archive and a full report for publication within two years of the completion of the archaeological fieldwork.
Reason - To safeguard the recording and inspection of matters of archaeological importance on the site in accordance with Policy ENV9 of the South Oxfordshire Local Plan 2035 and the NPPF (2023).