The development to which this permission relates must be begun not later than the expiration of three years beginning with the date of this permission.
Reason: By virtue of Sections 91 to 95 of the Town and Country Planning Act 1990 as amended by section 51 of the Planning and Compulsory Purchase Act 2004.
That the development hereby approved shall be carried out in accordance with the details shown on the following approved plans, C5347-13-C01, C5347-12-C01, C5347-102-P01, C5347-105-P01, C5347-103-P01, C5347-106-P01, C5347-100-P02, C5347-101-P01, C5347-02-P03 and C5347-05 C04, except as controlled or modified by conditions of this permission.
Reason: To secure the proper planning of the area in accordance with Development Plan policies.
A Construction Traffic Management Plan (CTMP) shall be submitted to and approved in writing by the Local Planning Authority prior to the commencement of development. The approved CTMP shall be implemented prior to any works being carried out on site, and shall be maintained throughout the course of the development.
Reason: In the interests of highway safety and to mitigate the impact of construction vehicles on the surrounding highway network, road infrastructure and local residents, particularly at morning and afternoon peak traffic times and in accordance with Policy TRANS5 of the South Oxfordshire Local Plan 2035.
Related application(s):
P25/S1518/DISThe applicant, or their agents or successors in title, shall be responsible for organising and implementing an archaeological monitoring and recording action, to be maintained during the period of construction/during any groundworks taking place on the site. The archaeological monitoring and recording action shall be carried out by a professional archaeological organisation in accordance with a Written Scheme of Investigation that has first been approved in writing by the Local Planning Authority.
Reason: To safeguard the recording and inspection of matters of archaeological importance on the site in accordance in accordance with Policy ENV9 of the of the South Oxfordshire Local Plan 2035.
Related application(s):
P25/S1518/DISFollowing the approval of the Written Scheme of Investigation referred to in condition 4, no development shall commence on site without the appointed archaeologist being present. Once the archaeological monitoring and recording action has been completed its findings shall be reported to the Local Planning Authority, as agreed in the Written Scheme of Investigation, including all processing, research and analysis necessary to produce an accessible and useable archive and a full report for publication which shall be submitted to the Local Planning Authority within two years of the completion of the archaeological fieldwork.
Reason: To safeguard the identification, recording, analysis and archiving of heritage assets before they are lost and to advance understanding of the heritage assets in their wider context through publication and dissemination of the evidence in accordance with Policy ENV9 South Oxfordshire Local Plan 2035.
No development shall take place (including demolition, ground works, vegetation clearance) until a construction environmental management plan (CEMP: Biodiversity) has been submitted to and approved in writing by the local planning authority. The CEMP (Biodiversity) shall include the following.
a) Risk assessment of potentially damaging construction activities.
b) Identification of biodiversity protection zones .
c) Practical measures (both physical measures and sensitive working practices) to avoid or reduce impacts during construction (may be provided as a set of method statements).
d) The location and timing of sensitive works to avoid harm to biodiversity features.
e) The times during construction when specialist ecologists need to be present on site to oversee works.
f) Responsible persons and lines of communication.
g) The role and responsibilities on site of an ecological clerk of works (ECoW)
or similarly competent person.
h) Use of protective fences, exclusion barriers and warning signs.
The approved CEMP shall be adhered to and implemented throughout the construction period strictly in accordance with the approved details, unless otherwise agreed in writing by the local planning authority.
Reason: To minimise impacts on biodiversity in accordance with the NPPF and Policy ENV2 of the South Oxfordshire Local Plan 2035.
Related application(s):
P25/S1518/DISPrior to the commencement of development a dimensioned plan shall be submitted to and approved in writing by the Local Planning Authority showing the location of the soakaway relative to the nearest structures.
The development shall be carried out in accordance with the approved details prior to the first occupation of the development hereby approved.
Reason: To prevent pollution and flooding in accordance with Policies ENV12 and EP4 of the South Oxfordshire Local Plan 2035.
Related application(s):
P25/S1518/DISNo installation of external lighting shall commence until a report detailing the lighting scheme, and how this will not adversely impact upon wildlife, has been submitted to and approved in writing by the LPA. The report (if external lighting is to be installed) shall include the following figures and appendices:
A layout plan with beam orientation
A schedule of equipment
Measures to avoid glare
An isolux contour map showing light spillage to 1 lux both vertically and horizontally, areas identified as being of importance for commuting and foraging bats, and locations of bird and bat boxes.
The approved lighting plan shall thereafter be implemented as agreed.
Reason: To limit the impact of light pollution from artificial light on nature conservation in accordance with paragraph 191 of the NPPF and Policy ENV12 of the South Oxfordshire Local Plan 2035.