The development to which this permission relates must be begun not later than the expiration of three years beginning with the date of this permission.
Reason: By virtue of Sections 91 to 95 of the Town and Country Planning Act 1990 as amended by section 51 of the Planning and Compulsory Purchase Act 2004.
That the development hereby approved shall be carried out in accordance with the details shown on the following approved plans, 20G Rev I, 23B Rev C, 24C, 21F, 03, 01 and 02, except as controlled or modified by conditions of this permission.
Reason: To secure the proper planning of the area in accordance with Development Plan policies.
The exterior of the development hereby permitted shall only be constructed in the materials specified on the plans/supporting documents hereby approved or in materials which shall previously have been approved in writing by the Local Planning Authority.
Reason: In the interests of the visual appearance of the development in accordance with Policies DES1, DES2, ENV6 and ENV8 of the South Oxfordshire Local Plan 2035.
The proposed window on the first floor of the south west side elevation (serving the en suite) of the development hereby permitted shall be obscure glazed and a fixed shut non-opening window where it falls below 1.7 metres above the floor level of the en suite.
Reason: To ensure that the development is not unneighbourly in accordance with Policy DES6 of the South Oxfordshire Local Plan 2035.
Prior to the commencement of any site works or operations, including demolition and site clearance relating to the development hereby permitted, an Arboricultural Method Statement and accompanying Tree Protection Plan shall be submitted to and approved in writing by the Local Planning Authority.
The Arboricultural Method Statement must include the following:
(1) A specification of any pruning or tree surgery works to any trees to be retained, to prevent accidental damage by construction or demolition activities;
(2) The specification and location of temporary tree protective fencing and any ground protection required to protect all retained trees in accordance with the current edition of BS 5837 ''Trees in relation to design, demolition and construction'', and details of the timing and duration of its erection;
(3) The definition of areas for the storage or stockpiling of materials, temporary on-site parking, site offices and huts, mixing of cement or concrete, and fuel storage;
(4) The means of demolition of any existing site structures, and of the re-instatement of the area currently occupied thereby;
(5) The route and method of installation of drainage or any underground services in the vicinity of retained trees; Consideration will be made to avoid siting of utilities and service runs within the Root Protection Area (RPA) of all trees to be retained. Only where it can be demonstrated that there is no alternative location for the laying of utilities, will encroachment into the RPA be considered. Methodology for any installation works within the RPA will be provided and must be in compliance with the current edition of NJUG 'Guidelines for the planning and installation and maintenance of utility apparatus in proximity to trees'.
(6) The details and method of construction of any other structures such as boundary walls in the RPA of retained trees and how these relate to existing ground levels;
(7) The details of materials and method of construction of any roadway, driveway, parking, pathway or other surfacing within the RPA, which is to be of a 'No Dig' construction method, in accordance with the principles with in Arboricultural Association Guidance Note 12 "The use of cellular confinement systems near trees" and in accordance with current industry best practice; and is appropriate for the type of roadway required in relation to its usage.
(8) Provision for the supervision of ANY works within the RPA of trees to be retained, and for the monitoring of continuing compliance with the protective measures specified, by an appropriately qualified arboricultural consultant, to be appointed at the developer's expense and notified to the Local Planning Authority, prior to the commencement of development; and provision for the regular reporting of continued compliance or any departure there from to the Local Planning Authority.
Thereafter the development shall be carried out in accordance with the approved details with the agreed measures being kept in place during the entire course of development.
Reason: To safeguard trees which are visually important in accordance with Policies ENV1, DES1, and DES2 of the South Oxfordshire Local Plan 2035.
Related application(s):
P25/S0999/DISA Construction Traffic Management Plan (CTMP) shall be submitted to and approved in writing by the Local Planning Authority prior to the commencement of development. The approved CTMP shall be implemented prior to any works being carried out on site, and shall be maintained throughout the course of the development.
Reason: In the interests of highway safety and to mitigate the impact of construction vehicles on the surrounding highway network, road infrastructure and local residents, particularly at morning and afternoon peak traffic times due to the proximity of the site to the primary school and in accordance with Policy TRANS5 of the South Oxfordshire Local Plan 2035.
Related application(s):
P25/S0999/DISNo development hereby permitted shall take place except in accordance with the terms and conditions of the Council's Organisational Licence (WML-OR150, or a 'Further Licence') and with the proposals detailed on plan "5 Plowden Park: Impact plan for great crested newt District Licensing (Version 1)" dated 15th July 2024.
Reason: In order to ensure that adverse impacts on great crested newts are adequately mitigated and to ensure that site works are delivered in full
compliance with the organisational licence (WML-OR150, or a 'Further Licence'), section 15 of the National Planning Policy Framework, Circular 06/2005 and the Natural Environment and Rural Communities Act 2006.
No development hereby permitted shall take place except in accordance with Part 1 of the Great Crested Newt Mitigation Principles, as set out in the District Licence (WML-OR150, or a 'Further Licence'), and in addition in compliance with the following: - Works which will affect likely newt hibernacula may only be undertaken during the active period for amphibians.
Reason: In order to ensure that adverse impacts on great crested newts are adequately mitigated and to ensure that site works are delivered in full compliance with the Organisational Licence (WML-OR150, or a 'Further Licence'), section 15 of the National Planning Policy Framework, Circular 06/2005 and the Natural Environment and Rural Communities Act 2006.