The development to which this permission relates must be begun not later than the expiration of three years beginning with the date of this permission.
Reason: By virtue of Sections 91 to 95 of the Town and Country Planning Act 1990 as amended by section 51 of the Planning and Compulsory Purchase Act 2004.
That the development hereby approved shall be carried out in accordance with the details shown on the following approved plans, P3809-01, P3809-02A, P3809-15A, P3809-16D and P3809-17B, except as controlled or modified by conditions of this permission.
Reason: To secure the proper planning of the area in accordance with Development Plan policies.
Prior to the commencement of development, with the exception of any demolition, a full surface water drainage scheme, shall be submitted to, and approved in writing by, the Local Planning Authority. The design of the surface water drainage system will be in accordance with the nonstatutory technical standards for sustainable drainage systems, including details of levels, size, position and construction of all drainage works. The drainage scheme must contain bio retention. The drainage scheme shall be sized to accommodate a minimum of the worst case 1 in 30 year storm, with evidence to demonstrate that the site can accommodate the worst case 1:100 year storm + 40% Climate Change storm, without any flows exiting up to this storm event and any storage on site not causing a nuisance or flooding to property. The approved scheme shall be implemented in accordance with the approved details prior to the occupation of the development hereby approved.
Notes
A contributing areas plan must be provided.
The network must be designed using the latest FEH software available. Currently, this is FEH22.
Cv values must be set at 0.95.
The building must contain a bio retention feature. This could be in the form of a rain water planter.
Full construction details of all surface water drainage components including hard standing areas.
Reason: To prevent pollution and flooding in accordance with Policies ENV12 and EP4 of the South Oxfordshire Local Plan 2035.
Related application(s):
P25/S1346/DISPrior to the commencement of the development hereby approved a scheme for the protection of the existing trees and hedges shown to be retained on approved plan P3809/15A shall be submitted to and approved in writing by the Local Planning Authority. Thereafter the development shall be carried out in accordance with the approved details.
Reason: In the interests of the visual appearance of the development and to help assimilate the development into its surroundings in accordance with Policies STRAT1, ENV1, DES1 and DES2 of the South Oxfordshire Local Plan 2035.
Related application(s):
P25/S1346/DISThe exterior of the development hereby permitted shall only be constructed in the materials specified on the plans and supporting documents hereby approved or in materials which shall previously have been approved in writing by the Local Planning Authority.
Reason: In the interests of the visual appearance of the development in accordance with Policies STRAT1, ENV1, DES1 and DES2 of the South Oxfordshire Local Plan 2035.
The rooflights hereby approved shall be set flush with the plane of the roof in which they are to be inserted.
Reason: In the interests of the visual appearance of the development in accordance with Policies STRAT1, ENV1, DES1 and DES2 of the South Oxfordshire Local Plan 2035.
Prior to implementation of the development, the existing means of access onto the 'Unnamed Road' shall be improved and laid out and constructed strictly in accordance with the local highway authority's specifications and all ancillary works specified shall be undertaken.
Reason: In the interest of highway safety in accordance with Policy TRANS5 of the South Oxfordshire Local Plan 2035.
Prior to the first occupation of the development hereby approved, the parking and turning areas shall be provided in accordance with the approved plans P3809/15A and P3089/16D and shall be constructed, laid out, surfaced, drained and completed to be compliant with sustainable drainage (SuDS) principles, and shall be retained unobstructed except for the parking of vehicles associated with the development at all times.