Conditions / Refusal Reasons
The development to which this permission relates must be begun not later than the expiration of three years beginning with the date of this permission.
Reason: By virtue of Sections 91 to 95 of the Town and Country Planning Act 1990 as amended by section 51 of the Planning and Compulsory Purchase Act 2004.
That the development hereby approved shall be carried out in accordance with the details shown on the following approved plans, LOC 001, BLO 001 and 230201357TGOS1, except as controlled or modified by conditions of this permission.
Reason: To secure the proper planning of the area in accordance with Development Plan policies.
The exterior of the development hereby permitted shall only be constructed in the materials specified on the plans/supporting documents hereby approved or in materials which shall previously have been approved in writing by the Local Planning Authority.
Reason: In the interests of the visual appearance of the development in accordance with Policies DES1, DES2 and ENV1 of the South Oxfordshire Local Plan 2035.
The development hereby permitted shall be constructed as an alternative to, but not in addition to, the development permitted by planning permission P22/S4331/HH.
Reason: To ensure that the character and appearance of the site and its surroundings are not harmed by cumulative development in accordance with Policies DES1, DES2 and ENV1 of the South Oxfordshire Local Plan 2035.