The development to which this permission relates must be begun not later than the expiration of three years beginning with the date of this permission.
Reason: By virtue of Sections 91 to 95 of the Town and Country Planning Act 1990 as amended by section 51 of the Planning and Compulsory Purchase Act 2004.
That the development hereby approved shall be carried out in accordance with the details shown on the following approved plans, 22 CFCL EX02 Rev A, 22 CFCL EX03 Rev A, 22 CFCL PE02 Rev A, 22 CFCL PE01 Rev B, 23 CFCL SL01, 22 CFCL SL01 Rev A, 22 CFCL EX01 Rev A and C-01, except as controlled or modified by conditions of this permission.
Reason: To secure the proper planning of the area in accordance with Development Plan policies.
No development shall commence, except for demolition and site clearance until a full surface water drainage scheme, including details of the size, position and construction of drainage works have been submitted to, and approved in writing by, the Local Planning Authority. The drainage scheme shall be designed to accommodate a 1 in 100 year storm + 40% CC and shall be implemented in accordance with the approved details prior to the occupation of the dwellings hereby approved.
Reason: To ensure the proper provision of surface water drainage and to ensure flooding is not exacerbated in the locality in accordance with policy EP4 of the South Oxfordshire Local Plan 2035.
Related application(s):
P23/S3803/DISNo development shall commence, except for demolition and site clearance until a full foul water drainage scheme has been submitted to and approved in writing by the Local Planning Authority. The scheme shall include details of the size, position and construction of the drainage scheme, all coupled with calculations to evidence this. Thereafter the scheme as approved shall be implemented prior to the occupation of the dwellings hereby approved.
Reason: To ensure the proper provision of foul water drainage and to ensure flooding and pollution is not exacerbated in the locality in accordance with policy EP4 of the South Oxfordshire Local Plan 2035.
Related application(s):
P23/S3803/DISNo above ground development (with the exception of demolition works) shall commence until a scheme for the landscaping of the site, including the planting of live trees and shrubs, has been submitted to and approved in writing by the Local Planning Authority. These details shall include schedules of new trees and shrubs to be planted (noting species, plant sizes and numbers/densities), the identification of the existing trees and shrubs on the site to be retained (noting species, location and spread), any earth moving operations and finished levels/contours, and an implementation programme. The scheme shall be implemented prior to the first occupation of the dwelling hereby approved and thereafter be maintained in accordance with the approved scheme. In the event of any of the trees or shrubs so planted dying or being seriously damaged or destroyed within 5 years of the completion of the development, a new tree or shrub or equivalent number of trees or shrubs, as the case may be, of a species first approved by the Local Planning Authority, shall be planted and properly maintained in a position or positions first approved in writing by the Local Planning Authority.
Reason: To help to assimilate the development into its surroundings in accordance with policies ENV1, DES1 and DES2 of the South Oxfordshire Local Plan 2035.
Related application(s):
P23/S3803/DISNo above ground development shall commence until details of all boundary walls, fences and any other means of enclosure have been submitted to and approved in writing by the Local Planning Authority. All such approved means of enclosure shall be erected prior to the first occupation of the development.
Reason: In the interests of the visual appearance of the development in accordance with Policies DES1 and DES2 of the South Oxfordshire Local Plan 2035.
Related application(s):
P23/S3803/DISNo windows shall be installed until details of the specification of the external glazing for all windows have been submitted to and approved in writing by the Local Planning Authority. For the avoidance of doubt, this condition requires the provision of a scheme to minimise visible light transmittance from inside to out. Thereafter, the glazing approved shall be installed and maintained in perpetuity in accordance with the approved details, unless otherwise agreed in writing by the Local Planning Authority.
Reason: To protect the appearance of the area, the environment and wildlife, and local residents from light pollution in accordance with policy ENV1 of the South Oxfordshire Local Plan 2035.
Related application(s):
P23/S3803/DISNo development shall commence, except for demolition and site clearance until a phased risk assessment has been submitted to and approved in writing by the local planning authority. The phased risk assessment must be carried out by a competent person in accordance with current government and Environment Agency Guidance and Approved Codes of Practice such as CLR11 'Model Procedures for the Management of Land Contamination' and BS10175 'Investigation of potentially contaminated sites'. Each phase shall be submitted to and approved in writing by the Local Planning Authority.
Phase 2 shall include a comprehensive intrusive investigation in order to characterise the type, nature and extent of contamination present, the risks to receptors, and if significant contamination is identified to inform the remediation strategy. Phase 3 requires that a remediation strategy shall be submitted to and approved by the local planning authority to ensure the site will be rendered suitable for its proposed use.
Reason - To ensure that any ground, water and associated gas contamination is identified and adequately addressed to ensure the safety of the development, the environment and to ensure the site is suitable for the proposed use in line with the NPPF and policy ENV11 of the South Oxfordshire Local Plan 2035.
Related application(s):
P23/S3803/DISThe development shall not be occupied until the approved remediation strategy referred to in condition 8 has been carried out in full and a validation report confirming completion of these works has been submitted to and approved in writing by the Local Planning Authority.
Reason: To ensure that any ground, water and associated gas contamination is identified and adequately addressed to ensure the safety of the development, the environment and to ensure the site is suitable for the proposed use in accordance with the NPPF and policy ENV11 of the South Oxfordshire Local Plan 2035.
The developer shall confirm in writing to the Local Planning Authority the presence of any unsuspected contamination encountered during the development. In the event of any contamination to the land and/or water being encountered, no development shall continue until a programme of investigation and/or remedial works to include methods of monitoring and certification of such works undertaken has been submitted to and approved in writing by the local planning authority.
Reason: To ensure that any ground, water and associated gas contamination is identified and adequately addressed to ensure the safety of the development, the environment and to ensure the site is suitable for the proposed use in accordance with policy ENV11 of the South Oxfordshire Local Plan 2035.
The dwelling shall not be occupied until an Electric Vehicle Charging Point has been installed.
Reason: To ensure sustainable forms of transport are provided in accordance with policy TRANS5 of the South Oxfordshire Local Plan 2035.
No dwelling shall be occupied until the parking and turning areas have been provided in accordance with drawing no. 22 CFCL SP01, Rev A. The parking and turning areas shall be constructed, laid out, surfaced, drained and completed to be compliant with sustainable drainage (SuDS) principles, and shall be retained unobstructed except for the parking of vehicles associated with the development at all times.
Reason: In the interests of highway safety and in accordance with policy TRANS5 of the South Oxfordshire Local Plan 2035.
The development hereby permitted shall only be constructed in the materials specified on the plan hereby approved or in materials which shall previously have been approved in writing by the Local Planning Authority.
Reason: In the interests of the visual appearance of the development in accordance with policies DES1 and DES2 of the South Oxfordshire Local Plan 2035.
No external lighting shall be provided on site other than that which has first been permitted in accordance with a lighting scheme submitted to and approved in writing by the Local Planning Authority prior to the installation of any external lighting. Any external lighting provided shall be implemented only in accordance with the approved details and directed downwards to prevent undue light spread/spillage, and shall thereafter be retained as such.
Reason: To protect the appearance of the area, the environment and wildlife, and local residents from light pollution in accordance with policy ENV1 of the South Oxfordshire Local Plan 2035.
Notwithstanding the provisions of Classes A, B and C of Part 1 Schedule 2 of the Town and Country Planning (General Permitted Development) Order 2015 (or the equivalent provisions of any order revoking and re-enacting that Order), there shall be no extensions or roof alterations to the dwelling hereby permitted without the prior grant of planning permission.
Reason: To safeguard the amenities of the occupiers of the adjoining properties and the character of the area in accordance with Policies DES1, DES2 and DES6 of the South Oxfordshire Local Plan 2035.