Conditions / Refusal Reasons
The development to which this permission relates must be begun not later than the expiration of three years beginning with the date of this permission.
Reason: By virtue of Sections 91 to 95 of the Town and Country Planning Act 1990 as amended by section 51 of the Planning and Compulsory Purchase Act 2004.
That the development hereby approved shall be carried out in accordance with the details shown on the following approved plans, 0019-GA-0001-P03, 0019-GA-0002-P03, 0019-GA-0003-P03, 0019-GA-0100-P08, 0019-GA-0102-P11, 0019-GA-0101-P10 and 0019-GA-0103-P05, except as controlled or modified by conditions of this permission.
Reason: To secure the proper planning of the area in accordance with Development Plan policies.
No development above slab level shall take place until a photographic schedule of all materials to be used in the external construction and finishes of the development hereby permitted has been submitted to and approved in writing by the Local Planning Authority.
Reason: In the interests of the visual appearance of the development in accordance with Policies DES1 and DES2 of the South Oxfordshire Local Plan 2035.
Prior to the commencement of any works of construction above foundation level, a full surface water drainage scheme based on full infiltration unless evidenced exhausted, including details of the size, position and construction of drainage works, shall be submitted to, and approved in writing by, the Local Planning Authority. The drainage scheme shall be designed on percolation testing results and to accommodate a 1 in 100 year storm + 40% CC and shall be implemented in accordance with the approved details prior to the occupation of the development hereby approved.
Reason: To prevent pollution and flooding in accordance with Policies ENV12 and EP4 of the South Oxfordshire Local Plan 2035.
Prior to the first occupation of the development hereby approved, the parking and turning areas shall be provided in accordance with the approved plan (0019-GA-0100 Rev P08) and shall be constructed, laid out, surfaced, drained and completed to be compliant with sustainable drainage (SuDS) principles, and shall be retained unobstructed except for the parking of vehicles associated with the development at all times.
Reason: In the interests of highway safety and in accordance with Policy TRANS5 of the South Oxfordshire Local Plan 2035.
Prior to first occupation, all carbon reduction energy efficiency measures shall be implemented in accordance with the Energy Statement hereby approved and a Verification Report shall be submitted to the Local Planning Authority and approved in writing. The Verification Report shall demonstrate (with photographic evidence) that the energy efficiency measures have been implemented. These measures shall be retained and maintained as such thereafter in accordance with the Energy Statement and Verification Report.
Reason: To ensure high standards of sustainable design and construction in accordance with Policy DES10 of the South Oxfordshire Local Plan 2035.
The first floor window in the east side elevation of the dwelling hereby permitted shall be glazed in obscure glass with a minimum of level 3 obscurity, and shall be fixed shut with the exception of a top hung openable fanlight (or other means of opening to be first agreed in writing by the Local Planning Authority) prior to the first occupation of the accommodation and it shall be retained as such thereafter.
Reason: To ensure that the development is not unneighbourly in accordance with Policy DES6 of the South Oxfordshire Local Plan 2035.