The development to which this permission relates must be begun not later than the expiration of three years beginning with the date of this permission.
Reason: By virtue of Sections 91 to 95 of the Town and Country Planning Act 1990 as amended by section 51 of the Planning and Compulsory Purchase Act 2004.
That the development hereby approved shall be carried out in accordance with the details shown on the following approved plans, CMP-001, 4 rev 1, 001, GA-DIDCOT-EN-21-3433-001 P8, 2278B-3, 2278B-1 and CMP-001, except as controlled or modified by conditions of this permission.
Reason: To secure the proper planning of the area in accordance with Development Plan policies.
No development shall commence unless and until a certificate confirming the agreement of an Offsetting Provider to deliver a Biodiversity Offsetting Scheme, totalling a minimum 4.5 habitat units has been submitted to and agreed in writing by the Local Planning Authority.
The written approval of the Council shall not be issued before the certificate has been issued by the Offset Provider. The details of biodiversity enhancements shall be documented by the Offset Provider and issued to the Council for their records.
Reason: To compensate for the net loss of biodiversity resulting from the development by providing biodiversity enhancements off site in accordance with Policy ENV3 of the SOLP and paragraphs 174 and 180 of the NPPF.
Related application(s):
P23/S0472/DISNo development hereby permitted shall take place unless and until a certificate from the Delivery Partner (as set out in the District Licence WML-OR112), confirming that all necessary measures in regard to great crested newt compensation have been appropriately dealt with, has been submitted to and approved by the local planning authority and the local authority has provided authorisation for the development to proceed under the district newt licence.
The Delivery Partner certificate must be submitted to this planning authority for approval prior to the commencement of the development hereby approved.
Reason: In order to adequately compensate for negative impacts to great crested newts in accordance with Policy ENV2 of the South Oxfordshire Local Plan 2035.
Related application(s):
P23/S0472/DISPrior to the commencement of any site works (including demolition or site clearance) a protected area shall be designated for all existing trees which are shown to be retained, and the trees shall be protected in accordance with a scheme which complies with the current edition of BS 5837: "Trees in relation to design, demolition and construction" that shall first have been submitted to, and approved in writing by, the Local Planning Authority. The agreed measures shall be kept in place during the entire course of development.
Reason: To safeguard trees which are visually important in accordance with Policies ENV1, DES1, and DES2 of the South Oxfordshire Local Plan 2035.
Related application(s):
P23/S0079/DISCycle parking facilities shall be provided prior to the occupation of the development hereby approved, in accordance with details to be submitted to and approved in writing by the Local Planning Authority, prior to the commencement of development.
Reason: To encourage the use of cycles as a means of transport in accordance with Policy TRANS5 of the South Oxfordshire Local Plan 2035.
Related application(s):
P23/S0079/DISPrior to commencement of any works at the site, a Construction Traffic Management Plan (CTMP) shall be submitted to and approved in writing by the Local Planning Authority. The approved CTMP shall be implemented prior to any works being carried out and shall be maintained throughout the course of the development. The CTMP's shall also state that no deliveries of plant or materials will take place to/from the site between the hours of 0730 - 0930 and 1600 - 1800. Reason: In the interests of highway safety and to mitigate the impact of construction vehicles on the surrounding highway network, road infrastructure and local residents, particularly at morning and afternoon peak traffic times.
Reason: In the interests of highway safety and to mitigate the impact of construction vehicles on the surrounding highway network, road infrastructure and local residents, particularly at morning and afternoon peak traffic times and in accordance with Policy TRANS5 of the South Oxfordshire Local Plan 2035.
Related application(s):
P23/S0079/DISPrior to first occupation, a record of the installed SuDS and site wide drainage scheme shall be submitted to and approved in writing by the Local Planning Authority for deposit with the Lead Local Flood Authority Asset Register. The details shall include:
· As built plans in both .pdf and .shp file format;
· Photographs to document each key stage of the drainage system when installed on site;
· Photographs to document the completed installation of the drainage structures on site;
· The name and contact details of any appointed management company information.
Reason: To ensure the proper provision of surface water drainage and to ensure flooding is not exacerbated in the locality in accordance with Policy EP4 of the South Oxfordshire Local Plan 2035.
Related application(s):
P23/S3139/DISPrior to the first occupation of the development hereby approved, the parking and turning areas shall be provided in accordance with the approved plans and shall be constructed, laid out, surfaced, drained and completed to be compliant with sustainable drainage (SuDS) principles, and shall be retained unobstructed except for the parking of vehicles associated with the development at all times.
Reason: To provided adequate car parking, in the interest of highway safety and to avoid localised flooding. in accordance with Policy TRANS5 of the South Oxfordshire Local Plan 2035.
The exterior of the development hereby permitted shall only be constructed in the materials specified on the plans/supporting documents hereby approved or in materials which shall previously have been approved in writing by the Local Planning Authority.
Reason: In the interests of the visual appearance of the development in accordance with Policies DES1 and DES2 of the South Oxfordshire Local Plan 2035.
The development hereby approved shall be implemented in strict accordance with all of the measures stated in section 5 of the supporting Ecological Impact Assessment Report (SLR, October 2022). 4 Bird boxes and 2 bat boxes shall be installed in suitable locations, informed by the project ecologist, prior to the first use of the development.
Reason: To minimise the ecological impacts of development, in accordance with Policies ENV2 and ENV3 of the SOLP, and paragraphs 174 and 180 of the NPPF.
No development hereby permitted shall take place except in accordance with the terms and conditions of the Council's organisational licence (WML-OR112) and with the proposals detailed on plan "Air Products: Impact Plan for great crested newt District Licensing (Version 2)", dated 14th September 2022.
Reason: In order to ensure that adverse impacts on great crested newts are adequately mitigated and to ensure that site works are delivered in full compliance with the organisational licence WML OR112 and in accordance with Policy ENV2 of the South Oxfordshire Local Plan 2035.
The developer shall confirm in writing to the Local Planning Authority the presence of any unsuspected contamination encountered during the development. In the event of any contamination to the land and/or water being encountered, no development shall continue until a programme of investigation and/or remedial works to include methods of monitoring and certification of such works undertaken. Where land contamination investigation/remedial works are required this must be carried out by a competent person in accordance with current government and Environment Agency Guidance and Approved Codes of Practice such as Land Contamination: Risk Management 2020 and BS10175:2011 +A2:2017 'Investigation of potentially contaminated sites' and submitted to and approved in writing by the local planning authority.