Description
Reserved Matters Application following Outline Approval (P15/S2902/O) in respect of the Community Centre including car parking, open space, landscaping and associated work.
Location
Land located to the North East of Didcot Didcot
Grid Reference
453205/191410
Applicant
Croudace Homes Ltd
Croudace Homes Ltd
The Spirella Building
Bridge Road
Letchworth Garden City
SG6 4ET
Agent
Croudace Homes
The Spirella Building
Bridge Road
Letchworth Garden City
SG6 4ET
Case Officer
Phil Moule
Telephone: 01235 422600
Email: planning@southoxon.gov.uk
Consultation / Notification
No further Representations on this application will be accepted.

Consultations / Notifications to date are shown below.

Name / Number
Date Sent
Response Date
 
Didcot Town Council
Council Offices
Britwell Road
DIDCOT
Oxon
OX11 7JN
06 05 2021
14 05 2021
 
Countryside Officer (South and Vale)
19 08 2021
27 09 2021
 
Drainage - (South&Vale)
19 08 2021
01 10 2021
 
Forestry Officer (South and Vale)
05 01 2023
18 01 2023
 
Env. Protection Team
05 05 2021
05 05 2021
 
Infrastucture Services
05 05 2021
 
Landscape Architect (South and Vale)
24 01 2022
15 02 2022
 
Leisure - South
06 05 2021
 
Oxfordshire County Council Single Response
05 01 2023
08 02 2023
 
Urban Design Officer (South and Vale)
06 05 2021
29 06 2021
 
Waste Management Officer (District Council)
24 01 2022
18 08 2021
 
26 Plym Drive
Didcot
OX11 7PG
22 05 2021
 
12 Trent Road
Didcot
OX11 7RB
22 05 2021
 
106 Infrastructure and Development
26 05 2021
 
Thames Water Development Control
25 05 2021
 
Application Type
Minor (Reserved Matters)
Application Progress
Date Received  
14th April 2021
Registration Date  
14th April 2021
Start Consultation Period  
5th May 2021
End Consultation Period  
26th May 2021
Target Decision Date  
10th May 2023
Decision
Reserved Matters - Approval on 4th May 2023
Conditions / Refusal Reasons
The development hereby permitted shall begin no later than two years from the date of approval of the last of the reserved matters to be approved. Reason: By virtue of Section 91 to 95 of the Town and Country Planning Act 1990 as amended by Section 51 of the Planning and Compulsory Purchase Act 2004.

That the development hereby approved shall be carried out in accordance with the details shown on the following approved plans, Plans: Location Plan DES/096/100 Rev 3 Site Layout DES/096/101 Rev 4 Surface Materials Plan DES/096/102 Rev 4 Enclosure & Lighting Plan DES/096/103 Rev 4 Parking & Refuse Strategy DES/096/104 Rev 4 Proposed Levels Plan DES/096/105 Rev 5 Vehicle Tracking Plan DES/096/106 Rev 3 Management Plan DES/096/107 Rev 3 Dimensioned Layout DES/096/108 Rev 4 Site Sections DES/096/109 Rev 3 Drainage Infrastructure Layout 708/130 Rev D Exceedance Flow Route 708/131 Rev D SW Catchment Area Plan 708/132 Rev D Community Centre Floor Plans DES/096/200 Rev 4 Community Centre Elevations DES/096/201 Refuse and Cycle Store DES/096/202 Rev 2 Landscaping Layout DES/096/500 Rev C LEMP Document CH014-008 Rev E Planting Plan CH014-013 LEMP Plan CH014-010 Rev B Soil Volumes CH014-011 Rev A Bench Details CH014-012 Supporting Documentation: Pattern Book DES/096/401 Reserved Matters Community Centre Specification DES/096/402 Sustainability Statement DES/096/403 Design Code Compliance Statement DES/096/404 Land Use Statement DES/096/405 Noise Impact Assessment Report Arboricultural Method Statement Rev A Drainage Strategy 708-130 Rev B SuDS Maintenance Rev B ACO Q-Brake Vortex Flood Risk & Compensation TN 002-820089-AQ Rev 2 Foul Water Drainage Calculations Surface Water Drainage Calculations 1 Surface Water Drainage Calculations 2 Surface Water Drainage Calculations 3 Surface Water Drainage Calculations 4 Surface Water Drainage Calculations 5 Surface Water Drainage Calculations 6 Surface Water Drainage Calculations 7 Surface Water Drainage Calculations 8 Croudace Phase 3A Drainage Statement Technical Note A252-R015 except as controlled or modified by conditions of this permission. Reason: To secure the proper planning of the area in accordance with Development Plan policies.

Notwithstanding the details shown on the approved elevations (DES/096/201 Rev 1) and the site sections (DES/096/109 Rev 3), level access shall be provided to the lobby access doors and the youth room exterior doors in accordance with the Community Centre Specification attached to the S106 Agreement. Reason: To avoid any ambiguity over the approved elevations and site sections and to make adequate provision for those whose mobility is impaired, in accordance with Policies TRANS2 and TRANS5 of the South Oxfordshire Local Plan 2035.

Prior to the commencement of development, a detailed surface water and foul water drainage plans shall be submitted to and approved in writing by the Local Planning Authority. The development shall be carried out in accordance with the approved details prior to the first occupation of the development hereby approved. Reason: To prevent pollution and flooding in accordance with Policies ENV12 and EP4 of the South Oxfordshire Local Plan 2035. Related application(s): P23/S2525/DIS

Prior to their implementation on site, details (to include type, size and appearance) of the two 'bridge crossing' points over the drainage ditch, as shown on the Drainage Infrastructure Plan Phase 3 708/130 Rev D shall be submitted to and approved in writing by the Local Planning Authority. The bridge design and implementation methodology must demonstrate how they will be constructed to avoid harm to the adjacent protected trees. The bridges shall thereafter be implemented in accordance with the approved details prior to the first occupation / use of the Community Centre. Reason: As these details have not been provided as part of the planning application material and are required to ensure the appropriate assimilation of the development into its surroundings in accordance with Policies ENV1, DES1 and DES2 of the South Oxfordshire Local Plan 2035. Related application(s): P23/S2651/DIS, P24/S2477/DIS

The community centre hereby approved shall be implemented and operated in accordance with the noise mitigation plan detailed in the Noise Impact Assessment Report, Willowbrook Community Centre, Energist UK, 26/11/2020 Reason: To safeguard the amenities of the occupiers of the proposed development in accordance with Policy ENV12 of the South Oxfordshire Local Plan 2035.

Prior to the first use of the development hereby approved, visibility splays from the means of access along the adjacent carriageway shall be provided in accordance with the provided drawings. Within the visibility envelopes, there shall be no obstructions whatsoever, inclusive of trees/planting/vegetation and/or boundary treatments above 600mm in height. Reason: To provide and maintain adequate visibility along the adjacent carriageway, in the interest of highway safety and in accordance with Policy TRANS5 of the South Oxfordshire Local Plan 2035.

Prior to the first use of the development hereby approved, the proposed parking and turning areas shall be provided in accordance with the approved plans and shall be constructed, laid out, surfaced, drained and completed compliant with sustainable drainage (SuDS) principles and thereafter, be retained unobstructed except for the parking of vehicles associated with the development at all times. Reason: In the interests of highway safety and in accordance with Policy TRANS5 of the South Oxfordshire Local Plan 2035.

Before commencement of any works, details of cycle parking to be provided to serve the development, shall be submitted to and approved in writing by the Local Planning Authority. Thereafter, the agreed cycle parking shall be provided before first occupation of the development and be maintained and retained all times. Reason: To encourage the use of cycles as a means of transport in accordance with Policy TRANS5 of the South Oxfordshire Local Plan 2035. Related application(s): P23/S2524/DIS

Prior to the first use of the development hereby approved, the whole of the estate roads and footpaths (except for the final surfacing thereof) that will serve the community centre shall be laid out, constructed, lit and drained and if required temporary or permanent traffic calming shall be put in place in accordance with Oxfordshire County Council's Specifications. Reason: In the interests of highway safety and to ensure a satisfactory standard of construction and layout for the development, in accordance with Policy TRANS5 of the South Oxfordshire Local Plan 2035.

No development shall be occupied until confirmation has been provided that either: (1) capacity exists off site to serve the development, or (2) a development and infrastructure phasing plan has been agreed with the Local Authority in consultation with Thames Water, or (3) all wastewater network upgrades required to accommodate the additional flows from the development have been completed. Where a development and infrastructure phasing plan is agreed, no occupation shall take place other than in accordance with the agreed development and infrastructure phasing plan. Reason: As network reinforcement works may be required to accommodate the proposed development and any reinforcement works identified will be necessary in order to avoid sewage flooding and/or potential pollution incidents, in accordance with Policies ENV12 and EP4 of the South Oxfordshire Local Plan 2035.
Appeal
No appeal lodged.
Updates
These Planning Application Details were returned live from our back office database, and as such are as up to date as when the page was retrieved.