Development shall not commence until details of the reserved matters: landscaping, appearance, layout, scale have been submitted to and approved in writing by the Local Planning Authority.
In the case of any reserved matter, application for approval must be made not later than the expiration of three years beginning with the date of the grant of outline planning permission.
Thereafter the development shall commence not later than whichever is the later of the following dates:
(a) the expiration of three years from the date of this permission; or
(b) the expiration of two years from the final approval of the reserved matters, or in the case of approval on different dates, the final approval of the last such matter to be approved.
Reason: By virtue of Sections 91 to 95 of the Town and Country Planning Act 1990 as amended by Section 51 of the Planning and Compulsory Purchase Act 2004.
That the development hereby approved shall be carried out in accordance with the details shown on the following approved plans, 22109_08_020-01 Rev A and 22109_08_020-02, except as controlled or modified by conditions of this permission.
Reason: To secure the proper planning of the area in accordance with Development Plan policies.
The reserved matters for the scheme shall be designed to secure an appropriate market housing mix in general conformity with the Oxfordshire Strategic Housing Market Assessment 2014 (Table 65), or subsequent update to the Strategic Housing Market Assessment.
Reason: To meet the housing market needs of the district in accordance with policies CSH1 and CSH4 of the South Oxfordshire Core Strategy 2027.
Prior to the commencement of the development hereby approved samples of all materials to be used in the external construction and finishes of the development hereby permitted shall be submitted to and approved in writing by the Local Planning Authority.
Reason: In the interests of the visual appearance of the development in accordance with Policy CSQ3 of the South Oxfordshire Core Strategy 2027 and Policies G2 and D1 of the South Oxfordshire Local Plan 2011.
Related application(s):
P18/S2425/DISPrior to the commencement of the development hereby permitted a scheme for the landscaping of the site, including the planting of live trees and shrubs, the treatment of the access road and hard standings, and the provision of boundary treatment shall be submitted to and approved in writing by the Local Planning Authority. The scheme shall be implemented prior to the first occupation or use of development and thereafter be maintained in accordance with the approved scheme. In the event of any of the trees or shrubs so planted dying or being seriously damaged or destroyed within 5 years of the completion of the development, a new tree or shrub or equivalent number of trees or shrubs, as the case may be, of a species first approved by the Local Planning Authority, shall be planted and properly maintained in a position or positions first approved in writing by the Local Planning Authority.
Reason: To help to assimilate the development into its surroundings in accordance with Policies CSEN1 and CSQ3 of the South Oxfordshire Core Strategy 2027 and Policies G2, C9 and D1 of the South Oxfordshire Local Plan 2011.
Related application(s):
P18/S2425/DISConcurrent with the submission of comprehensive details of the proposed landscape works, a maintenance schedule and a long term management plan for the soft landscaping works shall be submitted to and approved in writing by the Local Planning Authority. The schedule and plan shall be implemented in accordance with the agreed programme.
Reason: To help to assimilate the development into its surroundings in accordance with Policies CSEN1 and CSQ3 of the South Oxfordshire Core Strategy 2027 and Policies G2, C9 and D1 of the South Oxfordshire Local Plan 2011.
Related application(s):
P18/S2425/DISDetails of the LEAP and play equipment shall be submitted to and approved in writing by the Local Planning Authority before development commences.
Reason: To meet the need for children's play space in accordance with Policy CSI1 of the South Oxfordshire Core Strategy 2027.
Related application(s):
P18/S2425/DIS,
P19/S1501/DISPrior to occupation of the development hereby permitted the proposed means of access onto the site from the A4130 is to be formed and laid out and constructed strictly in accordance with the local highway authority's specifications and all ancillary works specified shall be undertaken.
Reason: In the interest of highway safety in accordance with Policy T1 of the South Oxfordshire Local Plan 2011.
The proposed vision splay shall be formed, laid out and constructed in accordance with detailed plans which shall be submitted to and approved in writing by the Local Planning Authority prior to the first occupation of the development. The vision splays shall thereafter be maintained in accordance with the approved details and not obstructed.
Reason: In the interest of highway safety in accordance with Policy T1 of the South Oxfordshire Local Plan 2011.
Related application(s):
P18/S2425/DISBefore any of the dwellings hereby permitted are first occupied, the whole of the estate roads and footpaths (except for the final surfacing thereof) shall be laid out, constructed, lit and drained and if required temporary or permanent traffic calming shall be put in place in accordance with Oxfordshire County Council's Specifications.
Reason: In the interests of highway safety and to ensure a satisfactory standard of construction and layout for the development, in accordance with Policy T1 of the South Oxfordshire Local Plan 2011.
Prior to the first occupation of the development hereby approved a turning area and car parking spaces shall be provided within the curtilage of the site so that motor vehicles may enter, turn round and leave in a forward direction and vehicles may park off the highway. The turning area and parking spaces shall be constructed, laid out, surfaced, drained and completed to be compliant with sustainable drainage (SuDS) principles in strict accordance with specification details to be submitted to and approved in writing by the Local Planning Authority prior to the commencement of development. The turning area and car parking spaces shall be retained unobstructed except for the parking and manoeuvring of motor vehicles at all times.
Reason: In the interests of highway safety and to ensure the provision of off-street car parking in accordance with Policies T1 and T2 of the South Oxfordshire Local Plan 2011.
Related application(s):
P18/S2425/DISAs indicated on the Development Framework Plan, a public right of way shall be secured through the site, with claimed footpath FP 'P' remaining on its claimed line. This will allow a continuous route between between footpath 189/35 to the west and the continuation of claimed footpath 'P' to the east .
Reason: To retain existing public rights of way in accordance with Policy T1 of the South Oxfordshire Local Plan 2011.
Prior to the first occupation of the development hereby permitted a Green Travel Plan and Travel Information Pack shall be drawn up and submitted to and approved in writing by the Local Planning Authority. Such plans are to include proposals for all travel by modes other than the private car for journeys to and from site. The submitted travel plan will be revised in line with Oxfordshire County Councils Travel Plan Teams comments and resubmitted for approval before first occupation of the site.The first residents of each dwelling shall be provided with a copy of the approved Travel Information Pack.
Reason: To promote the use of non car modes of transport in accordance with Policy CSM2 of the South Oxfordshire Core Strategy 2027.
Related application(s):
P18/S2425/DISA Construction Traffic Management Plan (CTMP) shall be submitted to and approved in writing by the Local Planning Authority prior to the commencement of development. The approved CTMP shall be implemented prior to any works being carried out on site, and shall be maintained throughout the course of the development.
Reason: In the interests of highway safety and to mitigate the impact of construction vehicles on the surrounding highway network, road infrastructure and local residents, particularly at morning and afternoon peak traffic times and in accordance with Policy T1 of the South Oxfordshire Local Plan 2011.
Related application(s):
P18/S2425/DISThe distance between the kerbside of the A4130 in its current alignment and the facade of any property on the development will measure a minimum distance of 39 metres in order to prevent the creation of a new AQMA.
Reason: To ensure satisfactory standards of air quality for the residents of the surrounding residential properties in accordance with policies G2 and EP1 of the a South Oxfordshire Local Plan 2011 and para's 17, 109, 110, 120 and 124 of the NPPF
Where on-site parking is provided for residential dwellings, EV charging points should be installed, a minimum of; 1 per household for each of the houses and 1 per every 10 flats.
Reason : To ensure satisfactory standards of air quality for the residents of the flats and surrounding residential properties in accordance with policies G2 and EP1 of the a South Oxfordshire Local Plan 2011 and para's 17, 109, 110, 120 and 124 of the NPPF.
No development shall take place until a detailed scheme for protecting the dwellings from the external noise environment of the area has been submitted to and approved in writing by the Local Planning Authority.
The scheme itself shall be designed, specified and constructed so that the sound insulation performance of the structure and the layout of the dwellings is such that the indoor ambient noise levels do not exceed the values detailed in Table 4 of BS 8233:2014 "Indoor ambient noise levels for dwellings". Noise levels in external amenity areas shall not exceed the desirable level of 50dB LAeq,T, as specified in Paragraph 7.7.3.2 of BS 8233:2014 "Indoor ambient noise levels for dwellings". Thereafter the development shall not be carried out other than in accordance with such approved scheme which shall be completed before any part of the accommodation hereby approved is occupied, unless the Local Planning Authority otherwise agrees in writing.
Reason: To safeguard the amenities of the occupiers of the proposed development in accordance with Policy EP2 of the South Oxfordshire Local Plan 2011.
Related application(s):
P18/S2425/DISNo development shall commence on site (including any works of demolition), until a Construction Method Statement, which shall include the following:
a) the parking of vehicles of site operatives and visitors;
b) loading and unloading of plant and materials;
c) storage of plant and materials used in constructing the development;
d) the erection and maintenance of security hoarding including decorative displays and facilities for public viewing, where appropriate;
e) wheel washing facilities;
f) measures to control the emission of dust and dirt during construction;
g) a scheme for recycling/disposing of waste resulting from demolition and construction works;
h) measures for the protection of the natural environment;
i) hours of construction, including deliveries;
has been submitted to, and approved in writing by, the Local Planning Authority. The approved Statement shall be adhered to throughout the construction period. The development shall not be carried out otherwise than in accordance with the approved construction methods.
Reason: To protect the occupants of nearby residential properties from noise disturbance in accordance with Policy EP2 of the South Oxfordshire Local Plan 2011.
Related application(s):
P18/S2425/DISPrior to any demolition and the commencement of the development a professional archaeological organisation acceptable to the Local Planning Authority shall prepare an Archaeological Written Scheme of Investigation, relating to the application site area, which shall be submitted to and approved in writing by the Local Planning Authority. Following the approval of the Written Scheme of Investigation and prior to any demolition on the site and the commencement of the development (other than in accordance with the agreed Written Scheme of Investigation), a staged programme of archaeological evaluation and mitigation shall be carried out by the commissioned archaeological organisation in accordance with the approved Written Scheme of Investigation. The programme of work shall include all processing, research and analysis necessary to produce an accessible and useable archive and a full report for publication which shall be submitted to the Local Planning Authority.
Reason: To enable an appropriate level of archaeological investigation of the area including excavation and recording, post excavation analysis and the publication of results in accordance with Policy CSEN3 of the South Oxfordshire Core Strategy 2027 and Policies G2, CON11, CON13, CON14 and E5 of the South Oxfordshire Local Plan 2011.
Related application(s):
P18/S2425/DISConcurrent with the submission of a reserved matters application, a Biodiversity Enhancement Strategy shall be submitted to and approved in writing by the Local Planning Authority. The strategy should demonstrate how the
development can achieve a no net loss of biodiversity overall compared to the biodiversity value of the site prior to development. The strategy should include both habitat and species enhancements and should use a suitable form of
biodiversity accounting to prove that no net loss can be achieved. Thereafter, the biodiversity enhancement measures shall be carried out and retained in accordance with the approved details.
Reason: To avoid a net loss of biodiversity in accordance with Policy CSB1 of the Core Strategy and government policy as stated in paragraphs 109 and 117 of the NPPF.
Related application(s):
P18/S2425/DISThe hours of operation for construction and demolition works shall be restricted to 08:00-18:00 Monday to Friday and 08:00-13:00 on a Saturday. No work is permitted to take place on Sundays or Public Holidays without the prior written authority of the Local Planning Authority.
Reason: To protect the occupants of nearby residential properties from noise disturbance in accordance with Policy EP2 of the South Oxfordshire Local Plan 2011.
The development hereby permitted shall only be carried out in accordance with the approved Flood Risk Assessment (FRA) and the following but not limited to the mitigation measures detailed within the FRA:
1. No built development or land raising shall be within Flood Zones 2 or 3.
Reason: To prevent an increased risk of flooding in accordance with the National Planning Policy Framework.
The development hereby permitted shall not be occupied until surface water drainage works have been carried out in accordance with details that have been first submitted to and approved in writing by the Local Planning Authority.
Reason: To prevent pollution and flooding in accordance with Policies EP1, EP4 and EP6 of the South Oxfordshire Local Plan 2011.
Development shall not commence until a drainage strategy detailing any on and/or off site drainage works, has been submitted to and approved by, the local planning authority in consultation with the sewerage undertaker. No discharge of foul or surface water from the site shall be accepted into the public system until the drainage works referred to in the strategy have been completed.
Reason: The development may lead to sewage flooding; to ensure that sufficient capacity is made available to cope with the new development; and in order to avoid adverse environmental impact upon the community in accordance with Policy EP1 of the South Oxfordshire Local Plan 2011.